Free Chinacertify Samples and Demo Questions Download
Microsoft exams Microsoft
Cisco exams Cisco
CompTIA exams CompTIA
HP exams HP
IBM exams IBM
Oracle exams Oracle
Adobe exams Adobe
Apple exams Apple
Avaya exams Avaya
BICSI exams BICSI
BlackBerry exams BlackBerry
Brocade exams Brocade
CA Technologies exams CA Technologies
CheckPoint exams Check Point
Citrix exams Citrix
CIW exams CIW
Cloudera exams Cloudera
CWNP exams CWNP
EC-Council exams EC-Council
EMC exams EMC
Exin exams Exin
FileMaker exams FileMaker
Fortinet exams Fortinet
GIAC exams GIAC
HRCI exams HRCI
ISACA exams ISACA
ISC2 exams ISC2
ISEB exams ISEB
iSQI exams iSQI
Juniper exams Juniper
LPI exams LPI
McAfee exams McAfee
Network Appliance exams NetApp
Pegasystems exams Pegasystems
PMI exams PMI
Riverbed exams Riverbed
SNIA exams SAP
SAS exams SAS
SOA exams SOA
Symantec exams Symantec
Tibco exams Tibco
VMware exams VMware
All certification exams

Microsoft 70-178 Exam - ChinaCertify.com

Free 70-178 Sample Questions:

Q: 1
You need to be able to send the custom Quick Access Toolbar to all users. What should you do?
A. Use the Reset all customizations option.
B. Use the Organizer tool.
C. Save the project as a Project 2010 template (.mpt) file.
D. Use the Export all customizations option.
Answer: A

Q: 2
You need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010. You need to achieve this goal while maintaining SharePoint synchronization. What should you do?
A. Use the Save to SharePoint feature and type the URL that contains the task list.
B. Open the SharePoint task list in Datasheet view and copy the tasks to a blank project file.
C. Use the New from SharePoint feature and type the URL that contains the task list.
D. Save the SharePoint task list to a Microsoft Excel file and use the Project Import Wizard.
Answer: B

Q: 3
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource.
What should you do?
A. Update the base project calendar.
B. Change the working time for the resource.
C. Change the maximum units for the resource.
D. Assign the resource only to tasks that are scheduled on the working days.
Answer: B

Q: 4
Your project has Subject Matter Experts (SMEs) who are consulted for each task. You need to create a single field that includes a list of SME names that can be associated with each task.
What should you do?
A. Create a task custom field that includes a lookup table custom attribute.
B. Enter the list of SME names on the Resource tab of the Task Information window.
C. Create a project custom field that includes a lookup table custom attribute.
D. Create a resource custom field that includes a lookup table custom attribute.
Answer: A

Q: 5
You attempt to print the task table and Gantt chart horizontally. However, the task names do not appear on each printed page. You need to ensure that the task names are printed on each page. What should you do?
A. Modify the settings in the Column Settings dialog box of the Task Name column.
B. Select the Task Name column and click Print.
C. Select the Task Name column and click Add to Timeline.
D. Modify the settings in the Field Settings dialog box of the Task Name column.
E. Modify the settings in the Page Setup dialog box.
Answer: A